EXTERIOR HOME SELECTIONS
SIDING
Cobblestone - James Hardie
APPROVED on:
ORDERED on:
STONE
Stoney Point Mosaic - Frederick Block Brick and Stone
APPROVED on:
ORDERED on:
WINDOWS
Anderson - Mostly 200 series, grills and details per approved
APPROVED on: 1/4/2024
ORDERED on: 1/5/2024
PROJECTED ARRIVAL: Late February
FRONT DOOR
Custom - Grand Entry Door
APPROVED on: 12/15/2023
ORDERED on: 12/21/2023
PROJECTED ARRIVAL: Late Febraury
GARAGE DOORS
Colonial 509 Glass Window with Elegant Short Door Style, White - Stoneberger Garage Doors
APPROVED on: 10/31/2024
ORDERED on:
PROJECTED ARRIVAL: March 2024
EXTERIOR DOORS
Awaiting final order to sign off.
APPROVED on:
ORDERED on:
PROJECTED ARRIVAL: Late February
KITCHEN
CABINETS
Cavelier Cabinets - Winchester
APPROVED on:
ORDERED on:
COUNTERTOPS
Still need to select.
DUE: May 2024
​
APPLIANCES
DUE 1/19/2024
APPROVED on:
ORDERED on:
PLUMBING FIXTURES
Still need to finalize.
DUE 1/19/2024
​
TILE / BACKSPLASH
DUE 3/15/2024
APPROVED on:
ORDERED on:
HOOD
DUE 3/1/2024
APPROVED on:
ORDERED on:
LIGHTING
DUE 2/15/2024
APPROVED ON:
ORDERED on:
MASTER BATHROOM
VANITIES
DUE 2/15/2024
​
COUNTERTOP
DUE: May 2024
​
PLUMBING FIXTURES
Still need to finalize.
DUE: 1/19/2024
FLOOR TILE
Still need to select.
DUE 2/15/2024
SHOWER TILE
Still need to select.
DUE: 2/15/2024
SHOWER FLOOR TILE
Still need to select.
DUE: 2/15/2024
ACCENT TILE
Still need to select.
DUE: 2/15/2024
ALL OTHER HOME SELECTIONS
VANITIES / SINKS FOR BATHROOMS
DUE 2/15/2024
​
CARPET
DUE: May 2024
​
FINISH CARPENTRY / TRIM
Still need to finalize.
DUE: March 2024
ALL TILE
Still need to select.
DUE 2/15/2024
HARDWOOD FLOORING
Still need to select.
DUE: 2/15/2024
INTERIOR DOORS
Still need to select.
DUE: March 2024
BOURBON ROOM FIREPLACE
APPROVED on: 01/19/2024
ORDERED on: 01/30/2024
GREAT ROOM FIREPLACE
APPROVED on: 01/19/2024
ORDERED on: 01/30/2024